Profit Z = 5x + 4y is to be maximised. The corner points of the feasible region are (0, 0), (8, 0), (6, 4) and (0, 6). What is the maximum profit and where does it occur?

Hint

The maximum of a linear objective lies at a corner point.

Show the answer

Answer: C. 46, at (6, 4)

Evaluate Z at each corner: (0, 0) gives 0, (8, 0) gives 40, (6, 4) gives 30 + 16 = 46 and (0, 6) gives 24. The largest value is 46, at (6, 4). The point (6, 6) is not a corner of the region.